Wind Project Status

JCC BRIEF FOR WIND PROJECTS

 

Name of the Project:

50MW WIND POWER PROJECT CHINA SUNNEC ENERGY (PRIVATE) LIMITED

 

CURRENT STATUS:

The project is on Early Harvest Program f the CPEC

 

Brief History:

Under the old upfront tariff regime, the project was supposed to achieve the Financial Close by 31st March 2015. The sponsors tried their best, but were not succeeded to achieve financial close.

The sponsors obtained extention in LOS from AEDB and waiting for NEPRA.

After tariff, the sponsors will sign Energy Purchase Agreement with CPPA (G) and Implementation Agreement (IA) with AEDB and achieve project Financial Close.

The tentative time period for Financial Close is expected by the end of February 2016.

After 18 months construction period, the project will start its Commercial Operations (COD) by end of August 2017.

 

MAJOR ISSUE:

No any

The financial Close of the project is expected in February 2016.

The project will be ready to supply power by September 2017.

 

Name of the Project:

49.5 MW WIND POWER PROJECT SACHAL ENERGY (PVT) LTD

 

CURRENT STATUS :

The project is on Early Harvest Program f the CPEC Projects with an investment of US$ 133 millions

 

MAJOR ISSUE:

SINOSURE POLICY ISSUE RESOLVED.

Sino sure has completed their Due Diligence process and sponsors also paid the requisite fees. The financial Close of he project is expected in December 2015 and project will be ready to supply power by June 2017.

 

Name of the Project:

100MW UEP Wind Power:

 

NO ISSUE:

The project is in construction phase and will be ready to provide electricity supply to national grid by October 2016.

 

Name of the Project:

49.5 MW Hydro china Dawood Wind Power Project:

 

NO ISSUE:

The project is in construction phase and will be ready to provide electricity supply to national grid by October 2016

 

Name of the Project:

PAKISTAN SECOND 100 MW WIND FARM BY CTGC:

The project is in the list of Actively Promoted Projects of CPEC. The feasibility study is in progress and the project will be ready to energize by 2017/18.